How to improve supplier on-time delivery.
Late supplier deliveries become your late deliveries. This guide starts with how aerospace customers define and measure supplier on-time delivery. It then covers the causes of late deliveries on both sides of the purchase order, and the steps that raise the number and keep it there.
By Sagemore, a supply chain, procurement, and contract consulting firm. Customer documents and public figures checked against the named sources on . Published .
Public examples, not your customer’s rules.
The supplier rules quoted here come from public customer documents, with their dates. Your purchase order and your customer’s current terms decide how your own delivery is measured.
What is supplier on-time delivery, and how is it calculated?
Supplier on-time delivery, or OTD, is the share of purchase order lines a supplier delivers on time in a period, out of all the lines due in that period. The aerospace industry’s Supply Chain Management Handbook (SCMH), in its 2018 metrics table, defines it as the number of purchase order lines delivered on time in the period against the number due in the period.
What counts as on time is set by the customer. The SCMH notes that the parameters vary from one customer to another, such as working or calendar days, and windows like five days early to two days late, or three days early to none late (IAQG SCMH, Metrics and KPI Definitions, 2018).
To build a measure, decide what is counted (orders, lines, or pieces), which date it is measured against, how early and how late still counts as on time, and whether a partial delivery counts.
How do aerospace customers measure supplier on-time delivery?
They measure against the date on the purchase order, by order line or by piece, with a short window or none at all. Four published examples, three from aerospace and defense and one from industrial automation, show how strict the rules are. Read your own purchase order, because each customer’s rule differs.
| Customer and document | What is counted | What counts as on time | Target or rating |
|---|---|---|---|
| Honeywell Technologies, General Terms and Conditions of Purchase, July 2026. Its aerospace business became a separate company on June 29, 2026. | Purchase order lines due in the month that were delivered on time and complete. Honeywell calls this OTTR/OTFP, measured to the purchase order request date. | On the date in the purchase order, or up to 3 days early. Up to 6 days early for international deliveries. No days late. | 100%. In a month the standard is missed, a 10% rebate on the invoice price of the goods that were not delivered on time. |
| GE Aerospace, Supplier Rating System, July 2024 | Pieces received on time against pieces required, over a trailing 26 weeks. | The training deck does not state an early or late window. Lines pulled in and delivered after the new due date are excluded. | Delivery is scored with commit participation: weeks with forward commits against weeks required. |
| Lockheed Martin, supplier scorecard, April 2021, and on-time delivery article, September 2024 | Lots and schedule quantities on each purchase order line. | Measured to the purchase order contract date, which Lockheed Martin calls a mutual agreement with its suppliers. No on-time credit when the rest of the line’s schedule is late. | Excellent 98% to 100%. Approved 95% to under 98%. Conditional 90% to under 95%. Unsatisfactory below 90%. |
| L3Harris Aerojet Rocketdyne, Performance Expectations, page undated | Contract line items against their due date. | Up to three calendar days late. A partial delivery counts as a failure if the full quantity is not delivered by the due date. | At least 90%. |
Each document can be revised. The one your purchase order cites applies. Lockheed Martin also writes that it uses suppliers’ on-time delivery measures to inform future sourcing decisions.
How are supplier deliveries trending?
Supplier deliveries across U.S. manufacturing were still slowing in October 2026, according to the Institute for Supply Management. Aerospace has its own published marks for what is unsatisfactory. These are third-party figures.
- Supplier deliveries
- Slower for the 11th month in a row in October 2026. The ISM Supplier Deliveries Index was 59.1, and above 50 means slower deliveries. Source: ISM Manufacturing PMI Report, October 2026, released November 2, 2026.
- Production material lead time
- 87 days on average in October 2026, three days more than in September, across U.S. manufacturing. Same source.
- One aerospace benchmark
- 80% on time for Boeing’s defense suppliers in 2023, up from 75% the year before, and below 85% over 12 months is unsatisfactory for an individual supplier, as reported by Reuters in March 2024. Reuters also reported, citing two suppliers, a stricter 90% bar in the defense unit. Boeing did not disclose company-wide figures.
How should a buyer measure supplier on-time delivery?
Measure every supplier the same way: by purchase order line, against the date the supplier accepted on the purchase order, with a stated window, and with partial deliveries counted as late. Publish the result monthly, and use the same measure your own customer uses on you where you can.
Measure against the accepted purchase order date, not a need date that changed after the order was placed. In our view, a measure to a date the supplier accepted is the fairest test, and the easiest to defend.
Measure your own side as well. The SCMH defines purchase order launch performance: the share of orders sent to suppliers in line with business needs and the supplier’s contractual lead time. It also tracks how many orders suppliers acknowledge on time. An order placed inside the supplier’s lead time is late before the supplier starts.
What is the difference between OTD and OTIF?
OTD, on-time delivery, checks whether a delivery arrived on time. OTIF, on time in full, also checks whether it arrived in the full quantity. Some customers’ rules already work like OTIF: Honeywell Technologies counts lines delivered on time and complete, and L3Harris Aerojet Rocketdyne counts a partial delivery as a failure.
Pick one, write it down, and apply it to every supplier. A scorecard where some suppliers are measured on time only and others on time and in full cannot be compared.
Why do suppliers deliver late?
The causes sit on both sides of the purchase order. Some sit with the buyer: orders placed inside lead time, wrong lead times in the planning system, and schedule changes. Others sit with the supplier: capacity, raw material, special process queues, and rework. Find which ones apply before asking anyone to try harder.
| Cause | How it shows | What fixes it |
|---|---|---|
| Orders placed inside lead time | The order is late the day it is sent. | Measure purchase order launch performance, and plan from correct lead times. |
| Wrong lead times in the planning system | Planned dates no supplier can meet. | Update lead times from actual receipts and from each supplier, at least once a year and when markets move. |
| Schedule changes and pull-ins | Dates moved earlier than the supplier’s lead time. | Change dates only with the supplier’s agreement, and do not count a pulled-in line as late if it was never accepted. |
| Capacity | One supplier late on many parts at once. | Share a forecast, agree capacity for your parts, and qualify a second source for the critical ones. |
| Raw material | Long and uncertain material lead times. | Stocking agreements, buying material ahead, or a long-term agreement that covers material. |
| Special process queues | Parts wait at heat treat, plating, or nondestructive testing. | Ask suppliers for their processor lead times, and qualify more than one approved processor. |
| Quality escapes and rework | Parts made on time, then rejected or reworked. | Find the root cause of each rejection, and fix the process, not only the part. |
| No acknowledgment or missing dates | Orders that no one at the supplier confirmed. | Require written acknowledgment of each order with a committed date. |
A share of late deliveries traces back to the customer. TRIGO, an aerospace quality services company, reported in January 2024 from its own preliminary research that 33% of late deliveries in the U.S. aerospace supply chain were the responsibility of the end customer. It is one company’s data from its own work. TRIGO’s report says it covers 18 months of delivery data, January 2022 to July 2023, from about 500 U.S. suppliers.
How do you improve supplier on-time delivery?
Get the measure right first, then fix your own side, then work with the suppliers. The last step is to use the result in sourcing.
Write one definition
What is counted, against which date, the window, and how partials count. Send it to every supplier.
Clean the dates
Each open purchase order line needs a date the supplier accepted. Correct lead times in the planning system from actual receipts.
Publish a monthly scorecard
On-time delivery, quality, and response, by supplier, with the late lines listed. A supplier that sees its own late lines can act on them.
Sort the late lines by cause
Group them by supplier and by cause, and start with the suppliers and causes that hold the most late lines.
Fix your own side first
Orders placed inside lead time, pulled-in dates, and missing acknowledgments are yours to fix, and fixing them earns the right to hold suppliers to their dates.
Agree recovery plans with the worst suppliers
Root cause, actions, owners, and dates, reviewed every week until the supplier is back on target.
Ask for forward commits
Have suppliers confirm the dates for the next weeks of the schedule, not only the next shipment. GE Aerospace scores this as commit participation.
Use the result in sourcing
Award new parts to suppliers that deliver, and qualify a second source where one does not. Tell suppliers that is how it works.
What changes when a defense order is rated?
A rated order under the Defense Priorities and Allocations System puts a deadline on the supplier’s answer. A supplier must accept or reject a DO rated order within 15 working days of receipt, and a DX rated order within 10 working days (15 CFR 700.13). An order placed for emergency preparedness can set a shorter time.
If the supplier cannot meet the requested date, it has to give the earliest date it can deliver. If a delay arises later, it has to give a new date. A supplier must also use rated orders with its own suppliers for the items needed to fill a rated order (15 CFR 700.15). An order below the greater of $125,000 or half the simplified acquisition threshold does not need the rating if delivery can be had on time without it (15 CFR 700.17). See our FAR and DFARS flow-down guide.
What mistakes hide late deliveries?
They sit in how the number is counted and in what is done with it. Counting rules can hide a late line. A number that no one reviews is useless even when it is right.
Moving the due date to the delivery date
Re-promised dates make every delivery look on time. Keep the original accepted date as the measure, and record changes separately.
Counting partials as on time
A partial delivery leaves the line short. Count it as late until the full quantity arrives.
Ignoring early deliveries
Early deliveries add inventory and receiving work. Set a window for early as well as late, as Honeywell does.
Measuring to a date the supplier never accepted
A need date changed after the order was placed is not the supplier’s date. Measure to the accepted date.
A scorecard with no conversation
A number sent each month with no review changes nothing. Review the worst suppliers with them, line by line.
Blaming suppliers for your own causes
Orders placed inside lead time and pulled-in dates are buyer-side causes. Fix them, or the supplier’s number never moves.
From operating experience.
- Supplier on-time delivery raised from 72% to 96% within 12 months, across a 200+ supplier aerospace and defense base.
- 90%+ supplier on-time delivery over a 12-month span across 60+ suppliers.
- 95% customer on-time delivery over a 12-month span.
These results were delivered while running supply chain organizations between 2017 and 2026. They are operator results, not client results. See all results
Supplier on-time delivery questions.
What is the formula for supplier on-time delivery?
Purchase order lines delivered on time in a period, divided by the lines due in that period, times 100. Some customers count pieces instead of lines. GE Aerospace, for example, counts pieces received on time against pieces required over 26 weeks.
What is a good supplier on-time delivery percentage?
There is no single benchmark. Two of the four customer documents on this page set a target, from at least 90% to 100%. Lockheed Martin’s scorecard rates 98% and above as excellent and below 90% as unsatisfactory, and Honeywell’s purchase terms set 100% as the standard.
Should on-time delivery be measured to the need date or the promise date?
Measure to the date the supplier accepted on the purchase order. A need date that changed after the order was placed was never the supplier’s commitment. Track the gap between the need date and the accepted date separately, because that gap is a planning problem.
Does an early delivery count as on time?
It depends on the customer’s window. Honeywell counts up to 3 days early as on time, and up to 6 days for international deliveries. Set an early window in your own definition, because early deliveries add inventory.
Does a partial shipment count as on time?
Not under strict rules. L3Harris Aerojet Rocketdyne counts a partial delivery as a failure if the full quantity is not delivered by the due date. Honeywell counts lines delivered on time and complete.
What should a supplier scorecard include?
Include on-time delivery, quality, and responsiveness, and list the late and rejected lines so the supplier can act on them. Keep the definitions the same for every supplier, and review the scorecard with the suppliers that miss.
How long does it take to improve supplier on-time delivery?
The causes set the time. Buyer-side causes, such as orders placed inside lead time, can be fixed sooner. Supplier capacity, raw material, and a second source take longer. Measure monthly so the trend is visible.
Sources and review date.
The customer rules and figures on this page were read from these sources on November 13, 2026. Customer documents are revised, so read the one your purchase order cites.
- IAQG Supply Chain Management Handbook, section 7.11.2, Metrics and KPI Definitions, February 28, 2018, as reproduced on pages 31 to 34 of a handout from the Aviation Suppliers Association 2018 annual conference.
- Honeywell Technologies, General Terms and Conditions of Purchase, revision July 2026, clause 3.
- GE Aerospace, Supplier Rating System training and FAQs, July 2024.
- Lockheed Martin, Supplier Scorecard, April 2021, and Importance of On-Time Delivery, September 27, 2024.
- L3Harris Aerojet Rocketdyne SupplierNet, Performance Expectations.
- ISM Manufacturing PMI Report, October 2026, released November 2, 2026.
- Reuters, Boeing defense suppliers’ on-time delivery in 2023, March 19, 2024, and Logistics Management, on TRIGO research, January 29, 2024.
- 15 CFR 700.13, acceptance and rejection of rated orders, and 15 CFR 700.15, use of rated orders with suppliers.
Not ready to talk? Start here.
Use these on your own. No form to fill in.
- Self-check: your supply chain in ten questionsYour score shows on screen, with where to look first.
- Tool: FAR and DFARS flow-down matrix19 clauses you can filter, with a spreadsheet to download.
- Guide: FAR and DFARS flow-down clausesWhat flows down, when, and what the supplier must do.
- Guide: what a supply chain consultant costsFee models, what drives the cost, and when to hire one.
Start with a 30‑minute conversation.
Tell us your on-time delivery number and how you measure it. On the call, we will tell you where we would look first.
Supply chain, procurement, and contract management services for aerospace, defense, and industrial manufacturers, for a single project or a continual requirement.
Start a conversation