How to reduce purchased material cost.

Across U.S. manufacturing, purchased materials, parts, and components equal more than half of the value of shipments. This guide covers how large that cost is, how prices have moved, the levers that lower it, and how to measure the result so the savings hold up.

By Sagemore, a supply chain, procurement, and contract consulting firm. Public figures checked against the named sources on . Published .

Public figures, not our results.

The cost and price figures on this page come from the U.S. Census Bureau and the U.S. Bureau of Labor Statistics, with dates. Recent price figures are preliminary and can be revised, so check the current series before you rely on one.

How much of a manufacturer’s spending is purchased material?

In the 2022 Economic Census, the cost of materials, components, packaging, and supplies used equaled about 54% of the value of shipments across U.S. manufacturing, and about 50% for aerospace products and parts. These are third-party figures, and they are shares of the value of shipments, not of total cost.

All manufacturing
About 54%. Materials, parts, and components cost $3.77 trillion against $7.05 trillion in value of shipments in 2022.
Transportation equipment
About 65% for NAICS 336, which includes aircraft, engines, parts, and vehicles.
Aerospace products and parts
About 50% for NAICS 3364, and about 70% for guided missiles and space vehicles (NAICS 336414).
Machine shops and foundries
About 33% and 40%. The first figure covers machine shops, turned products, and screws, nuts, and bolts together (NAICS 3327). The second covers foundries (NAICS 3315). These suppliers spend a smaller share of the value of shipments on material.
Source
U.S. Census Bureau, 2022 Economic Census, Manufacturing: Summary Statistics for the U.S., table EC2231BASIC. The shares are our arithmetic on the published figures.

How much have purchased material prices changed in the last year?

Steel and aluminum prices moved far more than the prices of made parts. In the Producer Price Index for October 2026 against October 2025, steel mill products rose about 33% and aluminum mill shapes about 23%, while fabricated metal products rose about 7%. These are preliminary third-party figures, released on November 13, 2026, and can be revised for up to four months.

Steel mill products
Up about 33%. Series WPU1017.
Aluminum mill shapes
Up about 23%. Series WPU102501.
Nickel alloy mill shapes
Up about 11%. Series WPU102504.
Titanium mill shapes
Up less than 1%. Series WPU102505.
Fabricated metal products
Up about 7%. Series PCU332---332---.
Goods bought by airplane makers
Up about 7%. The index of goods inputs to aircraft manufacturing, series WPUIP3364111.
Tariffs
Tariffs on steel, aluminum, and their derivatives differ by product, by country of origin, and by where the metal was melted. They are set out in Proclamation 11032 of June 1, 2026 and the proclamations it amends. A later one, Proclamation 11045 of July 20, 2026, changed the rules for primary aluminum. Ask each supplier to show the tariff as its own line on the quote.
Source
U.S. Bureau of Labor Statistics, Producer Price Index, not seasonally adjusted, October 2026 (preliminary) against October 2025. The changes are our arithmetic on the published index values. See the current PPI release.

What are the ways to reduce purchased material cost?

The main levers are the rows of the table below. Most categories need two or three of them, chosen after a spend baseline.

Material cost levers
LeverWhat it isFits whenWatch for
Consolidate suppliersMove spend from many suppliers to fewer, so each one earns more volume.The same kind of part is bought from many suppliers in small lots.A single source with no backup. Keep a second source qualified for critical parts.
Source competitivelyAsk qualified suppliers to quote a defined package of parts with the same drawings, quantities, and terms.Prices have not been tested for years, or the market has changed.Every new supplier needs qualification, and in aerospace usually a first article inspection. Count that cost and time.
Review should-costEstimate what a part should cost from its material, machine time, labor, setups, processes, overhead, and profit.A price looks high and the supplier will discuss what drives it.Use it to open a conversation about cost drivers, not to dictate a price.
Sign a long-term agreement with index pricingFix the conversion price for a term, and let the material part move with a named price index.Demand is steady and material is a large share of the part price.An index that does not match what the supplier buys, and terms that pay for raw material you never order.
Change the specificationRemove requirements that add cost without adding function: a material, a tolerance, a finish, or a test.Drawings carry requirements no one can explain.In aerospace and defense, a change can need engineering and customer approval and new qualification.
Standardize partsUse one part where several similar ones are bought today, especially hardware, seals, and fittings.The item master holds near-duplicates.Engineering has to approve each substitution, and old part numbers have to be closed.
Decide make or buyCompare the full cost of making a part with the full cost of buying it.Capacity, a new program, or a supplier problem forces the question.Counting only direct labor and material inside, and only the price outside.
Change how and when you buyBuy raw material from the mill or a stocking program, combine orders, set economic order quantities, and agree lead times.Rush orders and small lots carry premiums.Larger buys tie up cash. Weigh the price break against the inventory it creates.

How should a manufacturer start a material cost reduction program?

With a spend baseline and a few large categories, not with a request to every supplier for a price cut. The steps run from the baseline to savings that hold.

  1. Build a spend baseline

    Pull 12 months of purchase order lines and receipts: part, supplier, quantity, price, and date. The GAO describes spend analysis as knowing who buys, who supplies, and how much is spent for what.

  2. Group the spend into categories

    Examples are raw material, machined parts, castings and forgings, sheet metal, hardware, electronics, and special processes.

  3. Find what drives each price

    Look at material, machine time, labor, setups, special processes, freight, and tariffs. Ask suppliers to show the material and tariff lines separately.

  4. Pick the first categories

    Choose by size and by how much room there is: old prices, many suppliers for one part type, or a drawing nobody has reviewed.

  5. Choose the levers for each category

    Use the table above. Most categories need two or three levers.

  6. Run the sourcing event or negotiation

    Send a complete package: drawings, quantities, delivery, quality requirements, and terms. Compare total cost, not unit price alone.

  7. Put the result in an agreement

    Write the price, the term, any index, lead times, and stocking terms into a long-term agreement, so the price holds. See strategic sourcing and long-term agreements.

  8. Measure against the baseline, every quarter

    Report the price paid against the baseline price for the same parts, and keep cost avoidance separate.

What is the difference between cost reduction and cost avoidance?

Cost reduction is a lower price paid for the same item than the baseline price. Cost avoidance is a price increase that did not happen, such as a quote, a list price, or an index increase that was held off. Cost reduction shows in the next period’s results. Cost avoidance does not, so it should be reported on its own line.

The General Services Administration, as quoted by the Government Accountability Office in 2025, describes cost avoidance broadly as “paying less, using less, or obtaining more for the same cost.” Federal usage is wider than the one in this guide. The same GAO report found that officials at one agency assumed a cost avoidance rate for some contracts instead of measuring it. That is the risk: avoidance is easy to claim and hard to check.

Write the baseline down before any work starts: which parts, which prices, which period, and from which records. Then the result can be checked by anyone with the same records.

What is a should-cost review?

A should-cost review estimates what a part should cost if it is made efficiently, instead of accepting the supplier’s past price. The Federal Acquisition Regulation calls it a specialized form of cost analysis that does not assume historical costs reflect efficient operation (FAR 15.407-4).

For a machined or fabricated part, the estimate adds up the material by weight and price, the machine time by operation, setups spread over the lot size, special processes, inspection, packaging, freight, overhead, and a reasonable profit.

The value is in the conversation it opens. A gap between the estimate and the quote points to a question: a different material form, a long setup on a small lot, a process step that could be combined, or a tolerance that drives scrap.

Can a specification change lower material cost without hurting quality?

Yes, when the change removes cost without removing a function the part needs. The Federal Acquisition Regulation describes value engineering as an attempt to eliminate, without impairing essential functions or characteristics, anything that increases acquisition, operation, or support costs (FAR 48.101).

Start with the requirements no one can explain: a tighter tolerance than the assembly needs, a premium alloy where a common one would serve, a finish on a hidden surface, or a test repeated by two suppliers.

In aerospace and defense, the drawing may belong to your customer, and a change can need the customer’s approval, a new first article inspection, and requalification of the source. Count that time and cost before you count the saving.

What mistakes undo material cost savings?

A saving can be undone by any of the mistakes that follow.

  • Chasing unit price only

    A lower price from a supplier that delivers late, ships far away, or fails inspection can cost more in total. Compare freight, quality, lead time, and the inventory each choice needs.

  • Savings with no baseline

    Without a written baseline, a saving cannot be checked, and the next price increase erases it without anyone noticing.

  • Counting avoidance as reduction

    A price increase that was refused is worth reporting, but it does not lower next quarter’s cost. Report the two on separate lines.

  • Pressing a sole source

    A sole source with no alternative can raise prices, extend lead times, or drop the work. Qualify a second source before you negotiate hard.

  • Changing a part without requalifying it

    A cheaper material or a new supplier without the qualification your customer requires can create a quality escape that costs far more than the saving.

  • Buying off the agreement

    If buyers keep ordering from old suppliers or at old prices, the agreement saves nothing. Check purchase orders against the agreement every month.

From operating experience.

  • 125+ suppliers reviewed and the base consolidated 35%, with spend concentrated and quality issues reduced.
  • 27% lower cost, $225K saved, by onboarding the first U.S. key supplier for a high-volume commodity group.
  • Up to $19M in annual supplier spend managed.

These results were delivered while running supply chain organizations between 2017 and 2026. They are operator results, not client results. See all results

Material cost questions.

How do manufacturers reduce material costs?

By building a spend baseline, then using two or three levers in each large category. The levers are supplier consolidation, competitive sourcing, should-cost review, long-term agreements with index pricing, specification changes, part standardization, make or buy, and changes to how and when they buy.

What is the fastest way to lower material cost?

The fastest results come from categories where prices have not been tested for years, or where the same kind of part is spread across many suppliers. A competitive sourcing event or a consolidation in one of those categories shows results sooner than a specification change, which needs engineering approval and requalification.

Should we ask every supplier for a price cut?

No. The same percentage cut asked of every supplier ignores what drives each price, falls hardest on the suppliers you can least afford to lose, and is easy to give back later. Work category by category from a baseline instead.

How do you measure procurement savings?

Take the difference between the baseline price and the price paid for the same parts, and multiply it by the quantity bought. Report cost avoidance on its own line. Write the baseline, the period, and the records used before the work starts.

What is purchase price variance?

Purchase price variance is the difference between the standard cost of an item in your system and the price actually paid, multiplied by the quantity bought. It is a useful signal, but it depends on how the standard cost was set, so it is not a measure of savings on its own.

Does index pricing raise or lower cost?

Index pricing moves the material part of a price with a named public index, up or down. It does not lower cost by itself. It can take out the risk premium a supplier adds to a fixed price, and it makes the conversion part of the price open to negotiation.

How do tariffs affect material cost?

Tariffs on steel, aluminum, and their derivatives differ by product, by origin, and by where the metal was melted, and they have changed more than once in 2026. Ask each supplier for the country of melt and for the tariff as its own line, so it can be checked and so it comes off the price if the tariff changes.

Is supplier consolidation worth it?

It is worth it when one kind of part is spread across many suppliers in small lots. The added volume earns better prices and attention. Keep a qualified second source for critical parts, so consolidation does not create a single point of failure.

Sources and review date.

The figures on this page were read from these sources on November 13, 2026. They are third-party figures and will change.

Start with a 30‑minute conversation.

Tell us which categories you buy and how prices have moved. On the call, we will tell you where we would look first.

Start a conversation
© 2026 Sagemore, LLCTermsPrivacyCookie noticeMount Pleasant, South Carolina